Answer to Question #245246 in Biology for jak

Question #245246
An electronics company is hiring a part-time programmer to better calibrate one of its electronic devices. Four candidates for the position have stated how long it would take them to complete the project and what their hourly fee would be.

A 3-column table with 4 rows. Column 1 is labeled Programmer with entries Yogin; Amaya; Candice; Sheldon. Column 2 is labeled Fee per Hour with entries 40 dollars; 35 dollars; 32 dollars; 45 dollars. Column 3 is labeled Total Time with entries 12; 10; 15; 8.
Which programmer would be the most cost-effective choice for completing this project?
1
Expert's answer
2021-10-08T16:48:01-0400

Total sum for Yogin = 40 x 12 = $480

Total sum for Amaya = 35 x 10 = $350

Total sum for Candice = 32 x 15 = $480

Total sum for Sheldon = 45 x 8 = $360


Amaya will be the most cost-effective programmer for completing the project.


Need a fast expert's response?

Submit order

and get a quick answer at the best price

for any assignment or question with DETAILED EXPLANATIONS!

Comments

No comments. Be the first!

Leave a comment

LATEST TUTORIALS
New on Blog
APPROVED BY CLIENTS