Based on the above table, answer the following questions;
A. Calculating Expected Task Times
B. Draw the diagram that shows the relationship of the tasks
C. Calculate the project completion time
D. Develop the Early Start (ES) and Early Finish (EF) network
E. Develop the Late Start (LS) and Late Finish (LF) network
Step 1: Alongside to every engagement, note down the beginning and completion times.
Step 2: Calculate the length of the entire sequence by looking at the end moment of the last operation in the series.
Step 3: The crucial route is the series of actions with the longer time.