The number of men needed to cement a barangay road vanes directly with the length of the road at a constant

width and inversely with the number of days required to do the job. If a 30m road can be cemented by 10 men in

12 days how wide is the road? How many days will it take 50 men to cement a road that is 1 km long?


1
Expert's answer
2021-02-24T06:05:06-0500

Let "N=" the number of men needed, "L=" the length of the road, and

"t=" the number of days required to do the job. Then


"N=k\\cdot \\dfrac{L}{t}"

Given "N_1=10, L_1=30\\ m, t_1=12\\ days,"

"N_2=50, L_2=1\\ km=1000\\ m"

Find "t_2"


"\\dfrac{N_2}{N_1}=\\dfrac{k\\cdot \\dfrac{L_2}{t_2}}{k\\cdot \\dfrac{L_1}{t_1}}"

"N_2\\cdot\\dfrac{L_1}{t_1}=N_1\\cdot\\dfrac{L_2}{t_2}"

"t_2=t_1\\cdot\\dfrac{N_1\\cdot L_2}{N_2\\cdot L_1}"

"t_2=12\\cdot\\dfrac{10\\cdot 1000}{50\\cdot 30}=80(days)"

A 1 km road can be cemented by 50 men in 80 days.



Need a fast expert's response?

Submit order

and get a quick answer at the best price

for any assignment or question with DETAILED EXPLANATIONS!

Comments

No comments. Be the first!

Leave a comment

LATEST TUTORIALS
New on Blog