a shoe manufacturer produces midtoop and high top athletic shoes. cutting machines cut the fabric for shoes. stitching machine stitch the fabric. the cutting machines run 4 hours per day, and the stitching machines run 5 hours per day. a midtop shoe takes 3 minutes to cut and 2 minutes to stitch the profit is $13 on a midtop shoe and $16 on a hightop shoe. write the constraints


1
Expert's answer
2021-03-16T08:27:16-0400

Let the manufacturer makes "x" pairs of mid-top athletic shoes and "y" pairs of high-top athletic shoes per day.

"x\\geq0, y\\geq0"

A mid-top shoe takes 1 minute to cut.

A high-top shoe takes 3 minutes to cut.

The cutting machines run 4 hours per day.


"x+3y\\leq4(60)"

A mid-top shoe takes 2 minutes to stitch.

A high-top shoe takes 2 minutes to stitch.

The stitching machines run 5 hours per day.


"2x+2y\\leq5(60)"

Write the constraints


"\\begin{matrix}\n x+3y\\leq180 \\\\\n x+y\\leq150 \\\\\n x\\geq0 , y\\geq0\n\\end{matrix}"


Need a fast expert's response?

Submit order

and get a quick answer at the best price

for any assignment or question with DETAILED EXPLANATIONS!

Comments

No comments. Be the first!

Leave a comment

LATEST TUTORIALS
New on Blog
APPROVED BY CLIENTS