Find the critical path of the following network using the EST/LSTs.
Activity Preceding Activity Duration (days)
1 - 4
2 1 7
3 1 5
4 1 6
5 2 2
6 3 3
7 5 5
8 2, 6 11
9 7, 8 7
10 3 4
11 4 3
12 9, 10, 11 4
(b). Calculate the floats of the network diagram in part (a)