Question #237103

A small project is composed of 8 activities whose time estimates are listed below

Activity Time in weeks

i j Optimistic(a) Most likely(M) Pessimistic(b)

A 1 2 2 5 8

B 2 3 4 7 10

C 2 4 4 9 11

D 3 5 6 10 20

E 4 6 1 3 5

F 4 5 3 6 9

G 5 7 4 5 12

H 6 7 6 8 10

i) Develop a PERT network for the project .

ii) Determine the expected value and the variance for every activity.

iii) Calculate EST and LCT for every node.

iv) Find the critical path for the project .

v) Compute the probability of completing the project in 36 weeks .


0
Service report
It's been a while since this question is posted here. Still, the answer hasn't been got. Consider converting this question to a fully qualified assignment, and we will try to assist. Please click the link below to proceed: Submit order

Need a fast expert's response?

Submit order

and get a quick answer at the best price

for any assignment or question with DETAILED EXPLANATIONS!

Comments

No comments. Be the first!

Leave a comment

LATEST TUTORIALS
New on Blog
APPROVED BY CLIENTS