A small project is composed of 8 activities whose time estimates are listed below
Activity Time in weeks
i j Optimistic(a) Most likely(M) Pessimistic(b)
A 1 2 2 5 8
B 2 3 4 7 10
C 2 4 4 9 11
D 3 5 6 10 20
E 4 6 1 3 5
F 4 5 3 6 9
G 5 7 4 5 12
H 6 7 6 8 10
i) Develop a PERT network for the project .
ii) Determine the expected value and the variance for every activity.
iii) Calculate EST and LCT for every node.
iv) Find the critical path for the project .
v) Compute the probability of completing the project in 36 weeks .