identify the three conditions that a critical path must satisfy


1
Expert's answer
2021-09-28T09:18:42-0400

The three conditions that a critical path must satisfy are:-

All the project activities should be clearly defined and identified.

The technological sequence between the activities must be indicated.

A network must be constructed which shows the relative priority relationships.

The execution periods for each activity should be estimated.