Answer to Question #47102 in Quantitative Methods for Anurodh

Question #47102
A book binder has one printing press, one binding machine and manuscripts of seven
different books. The time required for performing printing and binding operations for
different printing and binding operations for different books are shown below:

Book 1 2 3 4 5 6 7

Printing Time 20 90 80 20 120 15 65
(Days)

Binding Time 25 60 75 30 90 35 50
(Days)

Find the optimum sequence of processing of the jobs that minimises the total time required.
Also compute the optimal time required.
1
Expert's answer
2014-09-30T09:20:46-0400
The answer to the question is available in the PDF file https://www.assignmentexpert.com/https://www.assignmentexpert.com/homework-answers/mathematics-answer-47102.pdf

Need a fast expert's response?

Submit order

and get a quick answer at the best price

for any assignment or question with DETAILED EXPLANATIONS!

Comments

Assignment Expert
15.07.21, 22:56

Dear Yuvraj, please use the panel for submitting a new question.


Yuvraj
16.06.21, 07:59

Jai Hind Industry uses MRP for its material planning. The table below provides the information about a particular component Z. The demand for this component is uncertain and in order to take care of the sudden spurt in the demand, a safety stock of 100 items if recommended. Week Weeks 1 2 3 4 5 6 7 Requi reme 50 nts 100 80 200 50 40 100 Order Quantity 300 on hand stock 300 2 weeks

Leave a comment

LATEST TUTORIALS
New on Blog
APPROVED BY CLIENTS