The following data for the activities of a project are available:
ACTIVITY IMMEDIATE PREDECESSOR DURATION (DAYS) A - 6 B - 4 C - 7 D A,B,C 5 E A,B,C 6 F D 9 G E 4 H F,G 8 I F,G 6 J H 7
Required: i. Draw the network, number the nodes, find the project completion time and calculate total, free and independent floats for the activities ii. When the activity duration of G is doubled, identify the critical path