Answer to Question #186847 in Programming & Computer Science for joana

Question #186847

6.

ACTIVITY PRECEDENCE DURATION (IN

DAYS)

A NONE 3

B A 12

C NONE 6

D B 1

E C, D 2

F E 1

G F 6

H F 3

I F 1

J G 3

K H, I, J 10

L K 2

M L 2

REQUIRED:

1. CONSTRUCT THE NETWORK DIAGRAM USING AON.

2. LIST ALL THE PATHS OF THE NETWORK AND THEIR RESPECTIVE DURATION.

3. IDENTIFY THE CRITICAL PATH/S AND ITS DURATION.

4. COMPUTE THE SLACK TIME FOR EACH ACTIVITY.

5. IDENTIFY THE CRITICAL AND THE NON-CRITICAL ACTIVITIES.


1
Expert's answer
2021-05-01T15:20:24-0400
Dear joana, your question requires a lot of work, which neither of our experts is ready to perform for free. We advise you to convert it to a fully qualified order and we will try to help you. Please click the link below to proceed: Submit order

Need a fast expert's response?

Submit order

and get a quick answer at the best price

for any assignment or question with DETAILED EXPLANATIONS!

Comments

No comments. Be the first!

Leave a comment

LATEST TUTORIALS
New on Blog
APPROVED BY CLIENTS