Using SJN, calculate the start time and finish time for each of these seven jobs that arrive one CPU cycle apart. Then indicate the order in which the jobs run to completion. (10) 18, 19, 20 2021 © The Independent Institute of Education (Pty) Ltd 2021 Page 8 of 8 Draw a timeline to understand when jobs arrive and finish. Job Arrival Time CPU Cycle A 0 4 B 1 11 C 2 4 D 4 1 E 5 9 F 7 4 G 8 2