Name two softwares that can be used to create visual information.


Types of softwares used for visual information



1 a. Discuss information privacy and methods for improving the privacy of information. (9pts)

b. Discuss information system issues that affect organizations, including the digital divide, electronic publishing, and the connection between the workplace and employees’ health.(8pts)

c. Describe green computing and the ways it can improve the quality of the environment. (8pts)

 


: Write a class named as Bus that contains the attributes which are mentioned below:

 The name of Bus.

 The direction of Bus (North (N), South(S), East(E), West (W))

 The position of Bus (from imaginary zero point)

The class has the following member functions:


Choose a domain where an expert system can help as assistant and provide at least 5 rules for

the knowledge base also provide the fact for working memory. 


Which of the following issues are of concern to Feminism?

A.The idea of democracy

B.Sexual stereotyping

C.Fairness and justice for all

D.Rejection of inferiority of women to men


1.a and d

2.b and c

3.c and d

4.b and d



List the libraries and URL of each of the three collection development policies that you identied from your literature search on the web indicating the year each of the policies of the three libraries was last reviewed.


6.

ACTIVITY PRECEDENCE DURATION (IN

DAYS)

A NONE 3

B A 12

C NONE 6

D B 1

E C, D 2

F E 1

G F 6

H F 3

I F 1

J G 3

K H, I, J 10

L K 2

M L 2

REQUIRED:

1. CONSTRUCT THE NETWORK DIAGRAM USING AON.

2. LIST ALL THE PATHS OF THE NETWORK AND THEIR RESPECTIVE DURATION.

3. IDENTIFY THE CRITICAL PATH/S AND ITS DURATION.

4. COMPUTE THE SLACK TIME FOR EACH ACTIVITY.

5. IDENTIFY THE CRITICAL AND THE NON-CRITICAL ACTIVITIES.


A mountain lake in Ifugao is stocked each summer with two species of fish A and B.

The average weight of the fish stocked is 4 kg for A and 2 kgs for B. Two foods, R and S

are available in the lake. The average requirement of a fish species A is 1 unit of R and 3

units of S each day. The corresponding requirement of B is 2 units of R and 1 unit of S. If

500 units of R and 900 units of S are available daily, how should the lake be stocked to

maximize the weight of fish supported by the lake? Solve using graphical method. Show

complete solution.

Required:

1. Formulate the following:

a. Decision variables

b. Objective function

c. Constraints

2. Graph

3. Identify feasible region.

4. Solve for the value of X and Y at each point.

5. Decision.


Ten sources, two with a bit rate of 80 Mbps, four with a bit rate of 20 Mbps and four

with a bit rate of 10 Mbps are to be combined using TDM. If the unit size is 10 bits

determine the following questions:

a) Input bit duration

b) Output bit duration

c) Frame rate